Project Planner 2023 – Free Excel template for Project Planning

If you are looking for a project management tool or software that can make project planning simpler, you have come to the right place. In this post, you will learn about a simple project planning framework and how to plan your projects smartly. You can download the free Project Plan template and start planning your projects immediately in Excel.

Project Planner Excel Template
Project Planner Excel Template – Project Scheduling, Timeline, Gantt Charts, project report & Resource management (utilization)

This post is written such that even if you are new to project planning, you will be able to quickly get started. By the end of this post, you will learn how to do the following using the template

  • To know when your projects will complete and if projects will complete by due dates (deadlines).
  • To understand resource utilization and identify opportunities for re-assignment to improve project completions.
  • To determine any shortage of resources, so that you can request additional resources.
  • To communicate to project stakeholders the readily printable project plan report, project timeline, project schedule (Gantt chart) and resource schedule.

Video Demo

What is Project Planning?

As a Project Manager, one of the key responsibilities is to plan the project before beginning the actual project work. This project planning is very crucial in the success of the project. For example, if our project is to build a home, then we want to have a clear project plan as to how we will build before we start building.

Outcome of Project Plan

Let’s assume you are the project manager and you are responsible for planning multiple projects at the same time. The outcome of the planning stage should address the following questions:

  1. When will all my projects complete? Will they complete by the target deadlines?
  2. How much will each project cost?
  3. How efficiently have I used the resources on project? (Utilization Rate)
  4. How can I communicate to my team so that they know which work needs to be done when?

If the answers to the above questions are not satisfactory, we will have more questions. We will address that later in this post.

Now, why is not easy to answer these questions? The foundation to answering these questions is to build the project schedule (who is going to work on which task for how long).

Project Schedule

To build project schedule, we need to consider a variety of factors

  • Resources
    • List of resources on the project
    • Available number of hours each day for each resource
    • Company holidays where work will not be done
  • Tasks/Work
    • Number of hours of work needed for each task
    • Any restrictions on Start Date (a task cannot start until you receive the machine needed)
    • Dependencies between tasks (a task can begin only after another is completed)
  • Resource-Task skill matching
    a. Assigning which resource should work on which task

Based on all the above input, we need to build the project plan schedule. This can get easily out of control if we do it manually. This is where we need the help of computers and software to build the schedule for us. Popular tools like Microsoft Project can do this. Now, you can also do it with a free project management tool.

Automatic Scheduling Engine

The template takes the above-mentioned inputs and automatically builds a project schedule. It lays out how we will complete the work needed for the project using the resources available. It clearly states who will be working on what task for how long on a given day.

It takes care of all the computations needed and saves us a ton of time and effort. For more, please read How does Automatic Scheduling Engine work.

Output of Project Planning template

Project Planning Template - Input and Output
Project Planning Template – Input and Output

The template provides the

  • Plan summary which details the key dates (start, end) for each project and its status
  • Visual Timeline view of projects
  • Resource Summary with utilization rates
  • Task schedule (Gantt Charts) for a project, a resource or all tasks
  • Resource availability and scheduled work by day

What if you are not happy with the project plan?

It may take a few iterations to land on a schedule that is acceptable. For example, in the first iteration, it might take really long to complete the project, in the next iteration it may cost a lot.

The levers a Project Manager has are

  • List of Resources
    • You can add or remove resources in the Project
  • Availability of those resources (standard hours, vacation)
    • You can change the available number of hours from each resource on the project
  • Assignment of resource to task
    • You can change the resource assigned to a task if possible
  • Scope of Task(s)
    • Sometimes, you can change the scope of a task and thus reduce the work needed

Once we land on an acceptable schedule, the Project Manager finds the answers to the original questions and shares in a project report with the Project sponsors to get approval. Once approved, what we have is a project plan. This will include key dates (milestones), the detailed schedule, cost estimates and resource utilization rates.

Project planner Excel Template

Benefits of project planner

  • Have Control over Project and Task dates
    • Project Start Dates can be restricted (optional) by providing preferred start date
    • Task Start Dates can be restricted (optional) by providing preferred start date
    • Preferred Project End Dates (aka Project due dates) can be given to compute if projects complete on time (optional)
    • Preferred Task End Dates can be given to compute if tasks complete on time (optional)
  • Control the order of Projects and Tasks by assigning priorities
    • Projects need to be prioritized and prioritization is followed when resources are assigned
    • Tasks can be prioritized and prioritization is followed when resources are assigned
    • Each task can have up to two predecessors (dependencies). They can be within project or from other projects. A task can begin only the day after its predecessors have completed.
  • Customize Capacity or Resource availability
    • Customize Weekends
    • Can handle any number of company holidays
    • Hours available to work per day (for the duration of the planning period) is customizable for each resource.
  • Notes
    • Each task is assigned to one and only one resource. A project can have multiple tasks and hence multiple resources.
    • Resource can be assigned to multiple tasks on the same day.
    • Planning is done at the granular unit of hours
    • Assign some tasks as milestones if needed

Free Downloads

How to plan projects in Excel?

Overview of steps

  1. [Data Entry] – Enter basic settings such as planning period, resources’ availability and company holidays
  2. [Data Entry] – Enter Project list
  3. [Data Entry] – Enter tasks, assigned resources and duration of work
  4. [Automated] – View Project plan summary, timeline view and resource summary report
  5. [Automated] – View Gantt Charts – Schedule for all tasks, one project or a resource
  6. [Automated] – View Resource Availability and Scheduled hours

Detailed Steps

The template has the following sheets: Home, Settings, Projects, Tasks, Plan Summary, Task Schedules, Resource View and Help.

If you are new to using Excel templates, please read this article on 3 tips before using Excel templates.

If you are not familiar with data entry in Excel tables, please read Introduction to data entry with Excel Tables.


Step 1. Enter basic settings

We begin by first selecting the planning period in the Settings sheet.

Project Plan Excel Template – Enter Project Planning Period Start and End Dates
Project Plan Excel Template – Enter Project Planning Period Start and End Dates


For example, I have entered the Nov 1, 2016 as the Planning Period Start Date and Dec 30, 2016 as the End date. The template can handle 60 days of planning period.

Next, we enter the list of resources (or employees) that are available to work on our projects.

Resources Available for Project Planning – Hours by Weekday and Cost Per hour
Resources Available for Project Planning – Hours by Weekday and Cost Per hour
  • We enter an ID for each Resource and the name.
  • We then enter the available hours for each weekday for each resource. The template allows each resource to have varying work hours.
  • We also enter the cost per hour for each resource. This input allows us to calculate the cost of the projects later.

Then, we choose which days are weekends in our organization.

Choose Company Weekends to display on Gantt Chart
Choose Company Weekends to display on Gantt Chart


As we have already entered availability for each resource separately, company weekends don’t provide any additional input to availability calculations. But this is used to display company weekends in the Gantt charts (which we will discuss later in this post).

Finally in the Settings sheet, we enter Company Holidays.

Enter Company Holidays to exclude from scheduling planned work
Enter Company Holidays to exclude from scheduling planned work


Step 2: Entering Project Data

Now that we are done with entering resource availability data, we move to the Project information. Let’s enter a list of our Projects.

Entering project Details in project planner template (click to see larger image)
Entering project Details in project planner template (click to see larger image)
  • Project ID and Project Name are required fields. They should be unique. Duplicate project IDs or Project Names will cause errors.
  • Project Priority is another required piece of information. This enables the template to schedule tasks in the order of priority. Priority of 1 indicates the highest priority project and Priority of 2 is the next important one.
  • Project Description is for your reference.
  • Preferred Start Date: If you would like the project to not start before a certain date, enter that date. The scheduling engine will not schedule any work for this project before this date.
  • Preferred End date: If there is a deadline or due date for a project, you can enter that here. The template will indicate if the project cannot be completed by this date.
  • Project Fixed Cost: The template can calculate resource cost separately. If there are other project costs, you can enter that amount here. Later, we will see that the template will add the fixed cost and the resource cost together as the total cost.
  • Project Plan Status: Please do not edit the field as it is calculated with a formula. If the project is missing any key piece of information, then the status will be ‘Error’. If there are no errors in data entry, the status will say ‘Planned’


Step 3: Entering Task Data

The last part of data entry is the task level detail. We would enter each task in all our projects. Let’s look at required input fields first.

Entering Task details for project planner – Required Inputs for planning
Entering Task details for project planner – Required Inputs for planning
  • Task ID should be unique
  • Enter Project Name and the Task Name
  • Enter Resource assigned to the task
  • Enter planned duration of the task in Hours Required

There are optional fields that are available to handle additional scenarios that you may face in project management.

Entering optional information about tasks – Preferred dates, Predecessors, Priority & Milestone
Entering optional information about tasks – Preferred dates, Predecessors, Priority & Milestone
  • Task Preferred Start Date: Just like we entered a Project Preferred Start Date in the Projects sheet, we can enter a preferred start date for tasks. The template will then make sure that no work for that task will be scheduled before that preferred start date. This is another way you have all the control on the project schedule.
  • Task Preferred End Date: Similar to Project Preferred End Date, if we have a due date for a specific task, enter that here. The template will then compare the expected end date with this preferred end date and tell us if the task will complete on time or not.
  • Predecessors: In most practical scenarios, tasks have dependencies between them. For example, in the image above, Task ID 2 has Task ID 1 as predecessor. This means Task #2 cannot begin before Task 1 is complete. Similarly Task ID 4 cannot begin until Task ID 3 is complete.
    • The template supports up to 2 predecessors per task. For example, Task ID 5 will not begin until both Task ID 2 and Task ID 4 are completed. This can get very complex for planning, but the template has calculations built-in to take care of this. So, we don’t have to worry about it. 🙂
    • If we don’t pay attention to setting predecessors correctly, we may end up with circular reference errors. How to avoid circular reference errors?
    • Note: In this template, the dependent tasks can begin only the day after the predecessors complete.
  • Task Priority: Just like we control the order of priority of projects, we can control the order of tasks within each project. Just enter the priority number. 1 is highest priority. This informs the template that higher priority tasks should be taken first. For example, if a resource is assigned to 2 tasks (one if priority 1 and second is priority 2), the template will schedule such that first task is completed before the resource moves to work on second task.
  • Milestone: Certain tasks can be labelled as milestones and they are highlighted in the Gantt Chart. Just enter ‘Yes’ for those tasks in the MILESTONE field.

Now, let’s discuss the very important Task Plan Result field.

View Task planning result instantly – will complete on time or late or not complete at all
View Task planning result instantly – will complete on time or late or not complete at all

Task Plan Result is a calculated field that will instantly inform whether the task will complete on time, complete late or not complete at all within the planning period. If there is any missing data input, it will also show an error.

This instant feedback is great for a project planner as you can change the resource assignment to see if the task will complete then.

Once we enter all the tasks we are done with our data entry. In the image above, I have entered 13 tasks for 3 projects in total. 1 task (task ID 2) seems to be completing late (Expected End date > Preferred End Date). Task ID 13 will not complete at all within the planning period (by Dec 30, 2016).

Step 4: Viewing Project Plan Summary

The Plan summary sheet is all automated. It has 3 sections (Projects’ Summary, Timeline view and Resource Summary).

Projects’ Summary
Each project’s plan details are shown.

Project Plan – Summary of projects’ planning status, expected dates and cost
Project Plan – Summary of projects’ planning status, expected dates and cost


Dates when the project is expected to start and end are clearly shown.

You can just export to PDF and share the summary with your stakeholders.

Project Timeline view

We can also see the project timeline visually.

Project Timeline view - Visually see project schedule - planned duration with preferred end date
Project Timeline view – Visually see project schedule – planned duration with preferred end date


Resource Management Summary

One of the crucial parts of project management is effective resource management. Having a clear view of resource utilization during the project is essential to delivering a successful project.

The Resource Summary table shows each resource’s utilization rate and cost.

Utilization Rate = Hours scheduled / Hours Available

Resource Summary Report with Resource Utilization Rate and Resource Cost
Resource Summary Report with Resource Utilization Rate and Resource Cost

In addition, you can view the detailed number of Hours Available, Hours Scheduled, Days Available and Days Scheduled.
With the Plan Summary sheet, we have seen project level and resource level reporting. Next we can see the task level reporting as well.


Task Schedules

Task Schedules sheet provide three types of detailed schedules. All Tasks, Tasks from one specific project and Tasks assigned to one specific resource.

Three views of task schedules - All Tasks, Project view or Resource view
Three views of task schedules – All Tasks, Project view or Resource view

Once we choose a schedule type, there will be three sections of information.

  • Summary Metrics
  • Detailed Table with task dates, hours and planning result
  • Gantt chart view

Summary Metrics

For ‘All Tasks’, the summary metrics appear like this.

Task Schedule Summary Metrics for All Tasks
Task Schedule Summary Metrics for All Tasks

If we choose a specific project, then the summary metrics display change to present relevant project metrics.

Task Schedule Summary metrics for chosen project
Task Schedule Summary metrics for chosen project

If we choose a specific resource, then the summary metrics present relevant resource management metrics.

Task Schedule resource management metrics for chosen resource
Task Schedule resource management metrics for chosen resource

Detailed Task level Details

We can see each task listed below along with the key details such as expected start and end dates, hours required and scheduled, and the task plan result.

Task Schedule Report with Task Planning Result
Task Schedule Report with Task Planning Result


Gantt Chart view

In the Gantt Chart, we have option to view daily Gantt chart or weekly Gantt chart. We can also enter a start date of our Gantt chart.

Gantt Chart view of Project schedule – Number of hours of work scheduled
Gantt Chart view of Project schedule – Number of hours of work scheduled


Gantt chart shows the number of hours scheduled for each day for the specific task. It also has the legend that explains the meaning of the different colors.

  1. Green: Work is Scheduled on this day.
  2. Gray: It is a company weekend day (resources may be available to work on weekends)
  3. Purple: Company holiday and no work will be scheduled on holidays.
  4. Red: Assigned Resource is not available to work on this task. This would indicate an opportunity to assign a different resource to see if that improves project completion.
  5. Blue: Milestone tasks’ completions are shown in Blue.

Resource View

Finally, we have the Resource View sheet which shows two key pieces of detailed information about resources.
We see the original resource capacity – number of Hours available by each resource on each day during project planning period.

Resource Management - View Original Capacity (hours available) for each resource by day
Resource Management – View Original Capacity (hours available) for each resource by day

This capacity is calculated based on the availability data we entered for each resource in the Settings sheet, and the Company holiday information.

Next, we also see how many hours each resource is scheduled for project work. In other words, this is the planned utilized time.

Resource Management - View Scheduled hours for each resource for each day
Resource Management – View Scheduled hours for each resource for each day


The difference between Hours Available and Hours scheduled is the Idle time or unutilized time.
From the above two images, we can see that the Web Designer is available 8 hours a day from Nov 1st to Nov 4th, but utilized only for 8 hours on Nov 4th. So, Nov 1st to Nov 3rd, Web Designer is not utilized at all.

I hope you find the template useful. Please provide your feedback via comments below. If you like the template, please share with others.


This basic template can plan up to 25 projects at a time and a total of 150 tasks for maximum Planning period of 60 days. To plan for more than 25 projects and 150 tasks and with a planning period of up to 1 year, please see Project Planner Advanced Excel template.

For more functionality like managing a project, creating customized Gantt charts, resource planning, check out our other products.

145 Comments

  • COuld you please let me know how you define “Ressource not available”.
    I mean if I plan one ressrouce for the next 2 weeks but the ressource won’t be available One day out fo those 2 weeks, how to do it?

    Reply
  • Hi, I think your template is great and provides a lot of functionality. I am testing it out with a small project and I cannot seem to change the start date from January 1900, should I start over or is there a way to fix this?

    Reply
    • Thank you.
      You should be able to change the start date. Please let me know which version of Excel you are using and which Operating system.
      I will follow up by email as well.
      Best wishes.

      Reply
  • I thought the basic template was free, or am I missing something? I purchased your event planner some years ago and still use it till this day…,it’s a great tool!

    Reply
    • Thank you. I am glad you like it.
      The template on this page is still free. I just upgraded the features of this free template earlier this month. It will look and work similar to the premium template, but limited on number of projects, tasks and project duration.
      Please let me know if there are any questions. Thanks. Best wishes.

      Reply
  • When you program a getaway journey, be accommodating concerning your spot.

    While it could be entertaining to determine a program by revisiting a well liked trip location, keeping some assortment in locations helps make your getaways much more
    unique and relaxing. Moreover, choosing a various location could be answer to protecting just a little dollars
    once the getaway funds are small.

    Reply
  • Dear Indzara ,

    I’m studying about multiple projects schedulling.

    Which algorthm did you use for scheduling multiple projects?

    Thank you

    Reply
    • Glad to hear.

      I am just applying priority based scheduling. We schedule the tasks for the highest priority project first. Within that project, we schedule the tasks based on the order in which they were entered in the Tasks sheet. Only after completing a higher priority task, resource can move to the next task.
      In the advanced template, we use some additional constraints and levers to control schedule. https://indzara.com/product/project-planner-advanced-excel-template/

      Best wishes.

      Reply
  • Fantastic work!

    Well done for creating the template.

    I have a question regarding the working hours. How can I change the working hours from 8 to 7.3?

    Thanks a lot

    Reply
    • Thank you.

      In the template, working hours can be set for each resource separately. You can enter the hours in the Projects sheet for each resource.
      Best wishes.

      Reply
  • The Project Planner – Basic (Free Excel template) is absolutely perfect for the needs of my organization. Thank you so much. You product is speaking the perfect language for me. Improvements are understandable, but please do not make any major changes, and please do not take the project away! Thanks again, and keep the support coming!

    Reply
  • Similar question as one you answered earlier, how can I extend this template for a project larger than 60 days.

    do you have a template that is for larger projects can you e-mail me an updaed templae

    Reply

Leave a Reply

Your email address will not be published. Required fields are marked *